Campbell Primary School P21 Project News Archive
- 21 Jan 2010 - Campbell Primary P21
Campbell Primary School - P21 bulk excavation completed, detailed excavation for piers and footings to be completed this week.
- 10 Feb 2010 - Campbell Primary P21
slab poured.
- 17 Jun 2010 - Campbell Primary P21
Campbell Primary P21 - Roof sheeting completed and roof plumbing completed. Internal framing and dry walling completed, eves still in progress, high level ceiling battened, wet area sheeting started, plumbing completed
- 10 Sep 2010 - Campbell Primary P21
Construction work is complete. Works progressing on the internal fit-off.
- 04 Nov 2010 - Campbell Primary P21
The BER Recognition Ceremony to celebrate the completion of the Campbell Primary School P21 project will be held on 05 November 2010 at 10:30 am
- 27 Jan 2011 - Campbell Primary P21
The BER Recognition Ceremony to celebrate the completion of the Campbell Primary School P21 project was held on 05 November 2010