Charnwood-Dunlop Primary School P21 Project Gallery

26 Feb 2010 - Footings being dug for the new multi purpose building

 

26 Feb 2010 - External footing complete for the new multi purpose building

 

26 Feb 2010 - Footing for the internal walls of the multi purpose building completed

 

26 Feb 2010 - Lower block works finished and preparations underway for the installation of the concrete slab

 

26 Feb 2010 - Freshly poured slab for the new multi purpose building

 

15 Mar 2010 - Completion of concrete slab

 

15 Mar 2010 - Steel Framework commenced

 

15 Mar 2010 - Steel Framework being installed

 

30 Mar 2010 - Steel work complete and internal block work 60% complete on the new multipurpose building

 

30 Mar 2010 - Steel work complete and internal blockwork 60% complete on the new multi purpose building

 

30 Mar 2010 - Steel work complete and internal block work 60% complete on the new multipurpose building

 

23 Apr 2010 - External brickwork complete and preparation for the external cladding underway

 

14 May 2010 - Electrical rough-in complete in the new multipurpose building

 

07 Jun 2010 - Insulation has been put in ready for the installation of wall and ceiling sheeting.

 

07 Jun 2010 - A covered walkway has been constructed to run between buildings. Its concrete slab will be poured next.

 

07 Jun 2010 - The new building with completed cladding. The windows have just been installed.

 

17 Jun 2010 - This image taken on 2 June shows wall and ceiling sheeting being installed in the new building.

 

18 Jun 2010 - Wall and ceiling sheeting has been installed in the multipurpose area, and is ready for painting. A kitchenette will be built at one end of this space and its servery window is visible in this photo.

 

18 Jun 2010 - The covered walkway, with reinforcing mesh installed, ready for the concrete slab to be laid. Rain delayed the concrete pour last week.

 

18 Jun 2010 - A concrete slab will be poured outside the front entrance.

 

28 Jun 2010 - The electrical rough-in has been completed throughout the new building. Interior painting has begun, with the rooms having been undercoated.

 

28 Jun 2010 - The construction of the new building has created a courtyard between it and existing buildings. Water tanks have been installed here to provide rainwater for toilet flushing and for landscaping use.

 

28 Jun 2010 - The slab has been poured, and the covered walkway is now completed.

 

06 Jul 2010 - With the internal painting finished, joinery is being installed in the Shared Learning Area.

 

06 Jul 2010 - Tiling and benches have been installed in the kitchenette in the multipurpose space.

 

14 Jul 2010 - Electrical fit off work is occurring in the new classrooms.

 

14 Jul 2010 - External work currently being done includes the construction of a path to lead to the new building.

 

08 Aug 2010 - External footpaths to give access to the new building have been completed.

 

08 Aug 2010 - A newly completed disabled access toilet.

 

08 Aug 2010 - Artificial grass has been installed in the courtyard shown earlier in a previous image.

 

08 Aug 2010 - A newly finished classroom. The new multipurpose building, which includes a practical activities area with kitchenette, a shared learning area and dedicated storage space has now been completed and was handed over to the school on 5 August 2010.

 

09 Sep 2010 - Another image of the finished building. This kitchenette opens off the Practical Activities Area.

 

09 Sep 2010 - The finished Practical Activities room.

 

09 Sep 2010 - Another image of a finished classroom, with an Interactive White Board installed.

 

09 Sep 2010 - The foyer in the newly completed multipurpose building, which features a Practical Activities Area with kitchenette, a Shared Learning Area and storage facilities. The building was handed over to the school on 5 August 2010 and the BER Recognition Ceremony was held on 8 September 2010.

 

09 Sep 2010 - The BER Recognition Ceremony to celebrate the completion of the new building was held on 8 September 2010. Standing with a group of students from the school are (from left to right)School Board Chair Ms Sue Gore-Phillips, ACT Senator Kate Lundy, Principal Ms Frances Dowling, School Network Leader Ms Joanne Garrisson, Senior Project Manager Grant Milthorp from GE Shaw, Project Architect Jeremy Mather from May + Russell Architects and P & C President Michael Pilbrow.