Charnwood-Dunlop Primary School P21 Project News Archive

  • 11 Feb 2010 - Charnwood-Dunlop Primary P21

Footings and lower block work have been completed. Internal building piers being installed

  • 02 Mar 2010 - Charnwood-Dunlop Primary P21

Concrete slab has been poured, monor earth works continuning

  • 30 Mar 2010 - Charnwood-Dunlop Primary School P21

Steel work complete and internal block work 60% complete on the new multipurpose building

  • 09 Apr 2010 - Charnwood-Dunlop Primary School P21

Roofing and blockwork in progress

  • 27 Apr 2010 - Charnwood-Dunlop Primary School P21

External brickwork is complete and preparation for external cladding is underway

  • 14 May 2010 - Charnwood-Dunlop Primary School P21

The electrical rough-in in the new building has been completed.

  • 31 May 2010 - Charnwood-Dunlop Primary School P21

All the services rough ins have now been completed and work on the external cladding is finished. Work is now underway on the internal partitioning.

  • 07 Jun 2010 - Charnwood-Dunlop Primary School P21

Internal wall sheeting and ceilings are being installed. The concrete slab for a covered walkway between buildings is ready to be poured.

  • 18 Jun 2010 - Charnwood-Dunlop Primary School P21

The pouring of the concrete for the covered walkway and at the entrance to the building was delayed by rain and is now due to take place this week. Inside the building all the wall and ceiling sheeting has been installed and is ready for painting work to start.

  • 28 Jun 2010 - Charnwood-Dunlop Primary School P21

Rainwater tanks have been installed to provide water that can be used for irrigating landscaping or flushing toilets. The external covered walkway is completed. Internal painting has begun.

  • 06 Jul 2010 - Charnwood-Dunlop P21

The new building is moving closer towards completion with internal painting completed, tiling work underway and joinery being installed. The next stage will be the laying of flooring material and the electrical fit-off.

  • 14 Jul 2010 - Charnwood-Dunlop Primary School P21

Internally the electrical fit-off is taking place. External work includes the construction of an access path to lead to the new building.

  • 08 Aug 2010 - Charnwood-Dunlop Primary School P21

The new multipurpose building, which includes a practical activities area with kitchenette, a shared learning area and dedicated storage space has now been completed and was handed over to the school on 5 August 2010.

  • 08 Aug 2010 - Charnwood-Dunlop Primary School P21

The BER Recognition Ceremony to celebrate the completion of the building works at the school will be held on 8 September 2010.

  • 27 Jan 2011 - Charnwood-Dunlop Primary School P21

The BER Recognition Ceremony to celebrate the completion of the building works at the school was held on 8 September 2010