  • 21 Jan 2010 - Curtin Primary P21

Curtin Primary School - P21 bulk excavation completed, detailed excavation for piers and footings to be completed this week.

  • 10 Feb 2010 - Curtin Primary P21

Slab poured.

  • 17 Jun 2010 - Curtin Primary P21

Curtin Primary P21 project – finalisation of external cladding and roofing, perimeter scaffolding removed, drywalling and ceiling installations continuing

  • 10 Sep 2010 - Curtin Primary P21

Most of the construction work is now complete, with external works starting including an improved disabled access ramp to link the new and old building. Works progressing on the internal fit-off.

  • 05 Nov 2010 - Curtin Primary School

A BER Recognition Ceremony to celebrate the completion of the Curtin Pimary School P21 project will be held on Friday, 26 November 2010 at 9:30am

  • 27 Jan 2011 - Curtin Primary P21

A BER Recognition Ceremony to celebrate the completion of the Curtin Pimary School P21 project was held on 26 November 2010