Evatt Primary School P21 Project Gallery

05 Jan 2010 - Bulk earth works being undertaken to create the multi purpose building

 

05 Jan 2010 - In slab services and reinforcement in place in preparation for the concrete sled to be poured

 

05 Jan 2010 - Insulation being put in place under the concrete slab

 

05 Jan 2010 - Concrete slab for new multi purpose building curing

 

05 Jan 2010 - Structural steel erection taking place for the new multi purpose building

 

04 Feb 2010 - Steel framework completed for the multipurpose building

 

04 Feb 2010 - First layer of external brick work commenced, insulation and secondary external brick layer to follow

 

04 Feb 2010 - Internal wall brick work has been commenced

 

04 Feb 2010 - First layer of external brick work nearing completion, insulation and secondary external brick layer to follow

 

26 Mar 2010 - Internal wall framing under construction in the new multipurpose building

 

26 Mar 2010 - Frame work going in for the clerestory windows to provide cross flow ventilation in the new multi purpose building

 

26 Mar 2010 - Covered walkway to link the new multipurpose building to the school under construction

 

26 Mar 2010 - External rendering complete on the new multipurpose building

 

26 Mar 2010 - Verandah at the back of the multipurpose building completed

 

09 Apr 2010 - Pin boards on storage cupboards in classroom area in new Multipurpose area

 

09 Apr 2010 - Pin boards on storage cupboards in second classroom area in new Multipurpose area

 

21 Apr 2010 - New landscaping work outside the new multipurpose building

 

21 Apr 2010 - New landscaping at the side of the multipurpose building

 

21 Apr 2010 - New ramp built to provide disabled access to the new multipurpose building

 

06 May 2010 - Play area for the new multipurpose building

 

06 May 2010 - Walkway linking school to the new building

 

06 May 2010 - Pin boards in classroom in the new building

 

06 May 2010 - Pin boards in second classroom

 

06 May 2010 - Accessible toilet

 

08 Jun 2010 - The new multipurpose building was completed and handed back to the school on 31 May 2010. This image shows the student entrance taken from the existing school building.

 

14 Jan 2011 - Front view of the new multipurpose building

 

14 Jan 2011 - Rear view of the new multipurpose building

 

14 Jan 2011 - Back view of the new multipurpose building