Evatt Primary School P21 Project News Archive
- 11 Feb 2010 - Evatt Primary P21
Brick work complete, insulation between brick layers installed. Roof sheeting on. Internal Frame work and electrical rough in complete
- 02 Mar 2010 - Evatt Primary P21
Roof sheeting on. Internal Frame work and electrical rough in complete. Ceilings and windows going in
- 09 Apr 2010 - Evatt Primary School P21
Internal fitout underway
- 27 Apr 2010 - Evatt Primary School P21
New landscaping has been installed around the new multipurpose building.
- 06 May 2010 - Evatt Primary School P21
Project completed 5 May 2010
- 31 May 2010 - Evatt Primary School P21
The new building has been handed over to the school and is now in use.
- 27 Jul 2010 - Evatt Primary School P21
BER Recognition Ceremony will be on 30 July 2010.
- 27 Jan 2011 - Evatt Primary School P21
A BER Recognition Ceremony to celebrate the completion of the Evatt Primary School P21 project was held on 30 July 2010