Florey Primary School P21 Project Gallery
16 Mar 2010 - Demolition of the internal areas of the hall and canteen that will be refurbished underway
26 Mar 2010 - Footings complete and formwork being installed in preparation for the installation of the concrete slab for the new multipurpose building
26 Mar 2010 - Footings complete and formwork being installed in preparation for the installation of the concrete slab for the new multipurpose building
21 Apr 2010 - Formwork and reinforcing steel installed in preparation for the slab of the new multipurpose building
14 May 2010 - Electrical rough-in complete as part of the refurbishment of the canteen as part of the school hall works
31 May 2010 - New benches and roller door were installed in the canteen as part of the hall refurbishment.
31 May 2010 - A view of the finished hall after refurbishment. This photo shows the newly extended stage, refinished floor and new audio-visual system.
18 Jun 2010 - An internal view of the new multipurpose area, with wall framing underway. A track will shortly be installed for a semi-operable wall which will enable the space to be divided into two when desired.
18 Jun 2010 - Another view of the multipurpose space. The area to the right hand side of the photo will become a wet area and toilets.
28 Jun 2010 - The electrical rough-in is underway. The next stage will be the installation of wall and ceiling sheeting.
14 Jul 2010 - Outside the new building brick paving is being laid in the courtyard which opens from it.
25 Aug 2010 - Joinery is being installed in the new building. This is a science bench in the multipurpose area.
25 Aug 2010 - A wide awning shelters the front entrance to the new building. Glass bi-fold doors will be installed in place of the temporary wooden hoardings later in the building process.
23 Sep 2010 - The multi-purpose space which can be used by the school or the community is being prepared for hand-over to the school. An operable wall allows this large space to be divided if desired.
23 Sep 2010 - A long work area for practical activities or science in the multipurpose building. The building has been completed and was handed over to the school on 6 September 2010.