Harrison School P21 Project Gallery

22 Mar 2010 - Block cleared and bulk earth works completed for the new multi purpose building

 

22 Mar 2010 - Reinforcing metal delivered for the concrete slab for the new multi purpose building

 

22 Mar 2010 - In ground services in place and blue metal in place in preparation for the new concrete slab

 

22 Mar 2010 - Concrete slab in place for the new multi purpose building

 

26 Mar 2010 - Structural steel being installed as part of the construction of the new performing areas and multipurpose building

 

26 Mar 2010 - Structural steel being installed as part of the construction of the new performing areas and multipurpose building

 

26 Mar 2010 - Structural steel nearing completion as part of the new performing areas and multipurpose building

 

09 Apr 2010 - Preparation for bricklaying for the new multipurpose building

 

21 Apr 2010 - Internal brickwork nearing completion in the new multipurpose building

 

07 May 2010 - Internal block works completed and roofing underway on the new performing arts building

 

07 May 2010 - Roofing being installed on the new performing arts building

 

18 May 2010 - Electrical rough in completed, window frames being installed in the new Performing Arts building.

 

31 May 2010 - Wall sheeting is underway in the new building.

 

31 May 2010 - This photo shows newly installed wall sheeting in what will be a Shared Learning Area. The recessed area in the centre will be fitted out as a kitchenette.

 

19 Jun 2010 - The external walls feature areas of coloured, glazed bricks. This photograph shows the brickwork almost completed.

 

19 Jun 2010 - The exterior of the new building. The roofing has been finished and the external cladding and brickwork is completed. The next stage will be the installation of the windows.

 

28 Jun 2010 - Ceiling battens have been fitted ready for the ceiling sheeting to be installed. In this photograph of one of the six new classrooms being constructed, low level louvres can be seen under the window. This is one of the design features that will help to make the building more energy efficient, by providing natural cross-flow ventilation and reducing the dependence on air-conditioning.

 

06 Jul 2010 - Work is currently underway on installing the heating, ventilation and cooling systems for the building. These are ventilation shafts.

 

06 Jul 2010 - These bifold doors will fold completely out of the way to give unimpeded access from the Performing Arts Building to what will be a paved area outside. This gives the ability for a performance or presentation to use the doorway as a stage, while the audience uses the paved area as outdoor seating.

 

14 Jul 2010 - The bifold doors seen from outside. Installation of windows and glazing throughout the building has been completed.

 

14 Jul 2010 - Work on the installation of ceilings has finished. With lighting fixtures now installed throughout the building, the electrical fit-off is close to completion.

 

14 Jul 2010 - A wall recess shown in a previous photograph is now being fitted out as a kitchenette. Joinery is also being installed in the wet area of the practical activities space.

 

08 Aug 2010 - New joinery is being constructed to provide storage.

 

08 Aug 2010 - Planter boxes are being built along this side of the new building.

 

08 Aug 2010 - A concrete forecourt is being laid as part of the hard landscaping work being done outside the building.

 

08 Aug 2010 - The classrooms have boldly coloured feature walls which echo the coloured panels on the exterior of the building. This photograph shows an operable wall, which can be either opened or closed to give more flexible use of the teaching space.

 

25 Aug 2010 - A kitchenette or wet area facility in the completed building.

 

25 Aug 2010 - A view of one of the new classrooms. The building has been completed and was handed over to the school on 24 August 2010.

 

10 Sep 2010 - Another image of the completed exterior of the new building.

 

10 Sep 2010 - An image of a completed classroom taken after the new building was handed over to the school.

 

10 Sep 2010 - A different view of the completed building, which provides six new classrooms, a multipurpose area with kitchenette and a shade awning adjoining the building. It was handed over to the school on 24 August 2010.

 

24 Feb 2011 - Completion of the new multipurpose building

 

24 Feb 2011 - The interior multipurpose building

 

24 Feb 2011 - The interior multipurpose building

 

24 Feb 2011 - The new multipurpose building

 

24 Feb 2011 - An image from the BER Recognition Ceremony held at Harrison School on 11 February 20011

 

24 Feb 2011 - The BER Recognition Ceremony to celebrate the completion of the BER P21 project

 

24 Feb 2011 - Address from Mary Porter AM MLA at the BER Recognition Ceremony