›› Site map    ›› Accessibility    ›› Languages    ›› Contact Us

About Us

Hawker Primary P21 Project Gallery

26 Mar 2010 - Existing school hall prior to the commencement of the works to refurbish and extend it

 

26 Mar 2010 - Existing school hall prior to the commencement of the works to refurbish and extend it

 

23 Apr 2010 - Site establishment for extensions to the existing hall

 

06 May 2010 - Excavation for in-ground services

 

06 May 2010 - Demolition of existing hall wall

 

20 May 2010 - Completing the demolition of the existing hall.

 

27 May 2010 - The curved footing to the left of the picture has been poured ready for the construction of a semi-circular band stage room in the new hall

 

07 Jun 2010 - Rain over the previous week has caused slight delays; however work to prepare for the construction of the slab has progressed. This photograph shows waffle pods delivered to the site. These are installed in the slab and assist in insulating the building.

 

19 Jun 2010 - This image shows the formwork for the waffle-pod slab. The new building will have two different floor levels to accommodate performing arts and music areas - this thicker slab will form the upper level.

 

19 Jun 2010 - Concrete being pumped into the conventional slab that will form the lower level of the new building.

 

19 Jun 2010 - Curved formwork is being constructed for the semi-circular band stage room.

 

28 Jun 2010 - The upper level of the slab has been poured. This will be the band stage.

 

07 Jul 2010 - The finished slab showing the three different levels.

 

08 Aug 2010 - Design modification work has been completed, and work is expected to begin during the next week on the erection of the building's steel framing. Access doorways have been cut into the existing part of the building to limk to the new section.

 

25 Aug 2010 - Work on the steel frame is proceeding. The tabs on the roof girders are for the attachment of purlins to support the roof sheeting.

 

25 Aug 2010 - With construction of the structural steel frame underway, it is becoming easier to see the shape of the extended hall. This image shows the curved outside wall of the new part of the building.

 

10 Sep 2010 - The roof framing has been installed, and blockwork construction of the walls is beginning.

 

10 Sep 2010 - Blockwork construction of the lower walls is well underway. This image shows formwork being constructed for the upper walls.

 

29 Sep 2010 - Mesh has been installed on the roof structure ready to roll out the roof insulation and install sheeting.

 

29 Sep 2010 - Formwork has been built to support the construction of the box guttering for the new building.

 

29 Sep 2010 - The internal framing of the building is taking shape.

 

29 Sep 2010 - The external walls are complete, roof insulation is in place and the roof sheeting has been installed. The building is now weathertight and internal work can now proceed more comfortably under cover.

 

12 Oct 2010 - Inside the building wall and ceiling sheeting is about to be installed.

 

01 Nov 2010 - Audio Visual room on the left hand side and multi purpose room on the right hand side

 

01 Nov 2010 - Construction of the new stage in the hall

 

01 Nov 2010 - Installation of ducting for the cooling and ventilation system and sheeting of hall walls

 

19 Nov 2010 - Preparation for ceiling installation

 

21 Jan 2011 - Painting underway in hall (foreground), and in AV room and learning unit (background)

 

21 Jan 2011 - Installation of lights and painting on stage

 

21 Jan 2011 - Gas radiant heating and light fittings being installed

 

21 Jan 2011 - Band stage prior to light installation

 

21 Jan 2011 - Band stage with lights and floor-covering installed

 

21 Jan 2011 - Gutters installed, tanbark laid, and path completed

 

14 Feb 2011 - Completion of the new Hall

 

14 Feb 2011 - New entry to the hall

 

14 Feb 2011 - Office/Audio visual room and multi-purpose room in hall

 

14 Feb 2011 - Access ramp to the Hall

 

14 Feb 2011 - Main stage and band area in Hall

 

14 Feb 2011 - Main stage in the Hall

 

08 Mar 2011 - Completion of the multipurpose hall

 

08 Mar 2011 - Fornt entrance of the multipupose hall

 

08 Mar 2011 - Rear view of the multipurpose hall

 

08 Mar 2011 - Front view of the multipurpose hall

 

09 Mar 2011 - Principal Mandy Cappello in the BER Recognition Ceremony

 

09 Mar 2011 - The BER Recognition Ceremony held to celebrate the completion of the BER works