Hawker Primary School P21 Project News Archive
- 11 Feb 2010 - Hawker Primary P21
Preliminary Sketch Plans approved, Final Sketch Plans in development
- 02 Mar 2010 - Hawker Primary P21
Preliminary Sketch Plans approved, Final Sketch Plans in development
- 29 Mar 2010 - Hawker Primary P21
Final sketch plans signed off, documentation in development
- 09 Apr 2010 - Hawker Primary P21
Site establishment is in progress
- 12 Apr 2010 - Hawker Primary School P21
Site establishment is in progress
- 07 May 2010 - Hawker Primary P21
An existing hall wall has been demolished in preparation for extensions to the hall, and excavation for in-ground services is taking place
- 20 May 2010 - Hawker Primary P21
Demolition of the existing hall is close to completion
- 27 May 2010 - Hawker Primary P21
Stormwater and sewer services have been diverted away from the new building, and a curved footing has been poured for the construction of a semi-circular band stage room in the new hall.
- 07 Jun 2010 - Hawker Primary P21
Recent rain has caused slight delays; however work is progressing on the construction of the slab. Waffle pods, which will assist in insulating the floor, are being installed. In the next stage, reinforcing rod is put in place between the waffle pods and the slab will be poured.
- 19 Jun 2010 - Hawker Primary P21
Work is continuing on the slabs for the new building. Formwork is in place for the upper level slab, and the lower slab has been poured. This lower level will be the main hall floor. A curved formwork is being constructed for the semi-circular band stage room.
- 28 Jun 2010 - Hawker Primary P21
Both levels of the slab are now completed. The next stage will be construction of the steel frame for the building.
- 07 Jul 2010 - Hawker Primary P21
There will be a temporary pause in external onsite work while minor design modification work is completed. Work is currently continuing on an internal school storeroom.
- 08 Aug 2010 - Hawker Primary P21
Weather permitting, work will commence during the coming week on the erection of structural steel for the extension.
- 25 Aug 2010 - Hawker Primary P21
Work is well underway on the erection of structural steel for the hall extension. Framing work will continue over the next few weeks.
- 10 Sep 2010 - Hawker Primary P21
Formwork construction and the laying of blockwork for the exterior walls is underway.
- 29 Sep 2010 - Hawker Primary P21
The external walls are substantially complete, and the roof has been installed. The focus of the work will now move to the interior of the building.
- 12 Oct 2010 - Hawker Primary P21
Inside the building a stack of wall sheeting is stacked ready to be installed. Wall and ceiling lining and the rough-in of electric cabling will be the next stages in construction.
- 21 Jan 2011 - Hawker Primary P21
Exterior near completion and installation of light fittings and floor coverings, and painting underway in hall
- 27 Jan 2011 - Hawker Primary P21
A BER Recognition Ceremony to celebrate the completion of works will be held on 4 March 2011