Kingsford Smith School P21 Project News Archive
- 11 Feb 2010 - Kingsford Smith School P21
Wall constructed to create new storage area
- 02 Mar 2010 - Kingsford Smith School P21
Wall constructed to create new storage area
- 12 Apr 2010 - Kingsford Smith School P21
Storage area in progress
- 19 May 2010 - Kingsford Smith P21
Installation of audio-visual equipment in the gym has commenced
- 31 May 2010 - Kingsford Smith P21
The upgrading of the gym's audio-visual equipment is continuing, with the installation of lighting bars as the next stage.
- 26 Jul 2010 - Kingsford Smith School P21
Work at the school has been completed. It included the provision of new stage lights with a motorised bar so lights can be rigged from floor level, a portable stage area, independent ventilation to a new kiln room in the Art Department and a new enquiries window constructed in the administration area.
- 26 Jul 2010 - Kingsford Smith School P21
BER Recognition Ceremony will be on 28 July 2010.
- 27 Jan 2011 - Kingsford Smith School P21
The BER Recognition Ceremony to celebrate the completion of works was held on 28 July 2010