Macgregor Primary School P21 Project News Archive

  • 12 Apr 2010 - Macgregor Primary

Internal fitout is in progress

  • 27 Apr 2010 - Macgregor Primary P21

Internal courtyard roof frame has been installed

  • 31 May 2010 - Macgregor Primary P21

The refurbishment of the Year 5 Teaching Area has been completed and has been handed over to the school. The internal courtyard has been roofed, and Crimesafe screen is being installed to make the area secure while still allowing for natural ventilation. In the library, track lighting is being installed.

  • 08 Jun 2010 - Macgregor Primary P21

Building work in the library has been completed although the shelving is still to arrive,and the area has been handed over to the school. The library now has an enclosed courtyard, a glassed meeting room, a resource room and reading rooms. The next stage of work is the refurbishment of the old Year 6 area.

  • 21 Jun 2010 - Macgregor Primary P21

The old Year 6 area has been gutted ready for refurbishment. The wet area has been removed and a dividing wall has been demolished.

  • 29 Jun 2010 - Macgregor Primary P21

All the furniture has now been delivered and installed in the library. Work is continuing in the Year 6 area, and new work has begun on refurbishments in the school hall. This will include painting the hall, building storage for the hall chairs, and work on the existing high level windows to provide improved cross-flow ventilation.

  • 26 Jul 2010 - Macgregor Primary P21

Repainting of the Year 6 area has been completed, and blinds have been fitted to the high-level windows for light and heat control. The Year 6 wet area has been finished, and custom joinery has been designed and installed to hold art supplies. In the school hall, refurbishment work is continuing with the construction of a new entrance doorway.

  • 08 Aug 2010 - Macgregor Primary P21

Work on refurbishments to the school hall have been completed. Refurbishment of the Year 6 area has also been completed, and the finished areas were handed back to the school ready for use on the first day of Term 3. Work has now commenced on an upgrade of the Year 3 wet area.

  • 27 Jan 2011 - Macgregor Primary P21

A BER Recognition Ceremony to celebrate the completion of works was held on 15 October 2010