Maribyrnong Primary P21 Project Gallery
22 Mar 2010 - Demolition of the existing dividing wall taking place as part of the hall refurbishment
22 Mar 2010 - Preparations being made for new structural beam to go in place as part of the hall refurbishment
22 Mar 2010 - New structural beam in place to create a larger school hall as part of the school hall refurbishment
26 Mar 2010 - Refurbished Learning Support Unit completed and ready to be handed back for school use
26 Mar 2010 - Refurbished Learning Support Unit completed and ready to be handed back for school use
26 Mar 2010 - Refurbished Learning Support Unit completed and ready to be handed back for school use
30 Mar 2010 - Electrical rough in and thermal chimneys being installed as part of the school hall refurbishment
30 Mar 2010 - Block works being installed to create a mini thermal labyrinth below the stage in the refurbished school hall
30 Mar 2010 - New external wall installed as part of the school hall refurbishment to allow the installation of a large stage within the hall.
30 Mar 2010 - New joinery being installed as part of the stage 1 refurbishment to the school craft/wet areas
31 May 2010 - Purpose-built curved wooden seating has been constructed along the front of the new stage.
31 May 2010 - To allow the school to continue using the facilities throughout the upgrade, the hall renovation was completed at one end of the building while the other end remained in use. Work on the canteen end has now begun, with internal demolition underway.
07 Jun 2010 - The last of the wet/craft areas have been completed and handed back for use by the school.
19 Jun 2010 - Stage Two of the hall refurbishment (in the old canteen end) is progressing. Here, accoustic wooden ceiling panels are being installed. When the refurbishment of this end has been completed the temporary wall visible in this photograph will be demolished and the hall will be restored to one large space.
25 Jun 2010 - The hall refurbishment is very close to completion. The temporary wall visible in previous photographs has been removed and the two stages of the refurbishment have been united. This image shows the whole hall. A small amount of work still needs to be done, replacing a glazed wall at the back of the hall.
06 Jul 2010 - A view from outside the hall of the old glazed wall that is currently being replaced. This will finish the hall refurbishment.
06 Jul 2010 - During the last months while internal refurbishments have been carried out in classrooms and the school hall, the exterior of the school has been repainted. This is the finished result.
27 Jul 2010 - The corridor is finished. It has been repainted and has a new, vinyl strip wood-look floor.
27 Jul 2010 - New entrance doors have replaced an old door as part of the upgrade, which is very close to completion.