Maribyrnong Primary School P21 Project News Archive
- 11 Feb 2010 - Maribyrnong Primary P21
Refurbished toilets handed over. Hoarding for hall construction complete and structural supports complete
- 02 Mar 2010 - Maribyrnong Primary P21
Wall sheeting being installed in stage 1 of the wet area rwefurbishment. Stage end of school hall demolished, services diversions underway
- 12 Apr 2010 - Maribyrnong Primary P21
Refurbishment of the Learning Support Unit is complete. Hall works are in progress.
- 27 Apr 2010 - Maribyrnong Primary P21
Framework under construction for the new stage in the renovated school hall
- 14 May 2010 - Maribyrnong Primary P21
First stage of the hall refurbishment is nearing completion. Half of the wet area refurbishments are underway.
- 19 May 2010 - Maribyrnong Primary P21
Hall works are continuing. The last of the craft/wet areas is almost completed.
- 31 May 2010 - Maribyrnong Primary P21
Eight refurbished craft areas have now been completed and handed back to the school. The last of the craft/wet areas is almost completed. Stage 2 of the school hall refurbishment has begun. Stage One has been completed, allowing the school to use this end of the hall while work moves into the canteen end of the building.
- 07 Jun 2010 - Maribyrnong Primary P21
The last wet craft areas have now been completed and have been handed back for use by the school.
- 19 Jun 2010 - Maribyrnong Primary P21
Stage Two of the hall refurbishment is progressing with the installation of wooden accoustic ceiling panels. The next work will be the installation of vinyl floor sheeting to match up with the completed floor on the other side of the temporary dividing wall.
- 28 Jun 2010 - Maribyrnong Primary P21
The temporary wall built as a divider during construction has been removed and vinyl flooring has been laid in the Stage Two end of the hall, carefully matched to the flooring already laid in Stage One. The hall refurbishment is almost complete, with a small amount of work remaining on a glazed wall at the end of the hall.
- 06 Jul 2010 - Maribyrnong Primary P21
Work is currently in progress to replace the glazed wall at the end of the refurbished hall. This will complete all the work at the school.
- 15 Jul 2010 - Maribyrnong Primary P21
New carpet has been laid throughout the teaching areas and a corridor has been refloored and repainted. New concrete has replaced the cracked and lifted paving outside the hall, and the new hall doors have been installed and almost finished.
- 27 Jul 2010 - Maribyrnong Primary P21
The work is very close to completion, with only some minor internal work to be finalised before the refurbished area is handed back to the school.
- 08 Aug 2010 - Maribyrnong Primary P21
All work in the school hall has been completed, and the hall was handed back to the school on 30 July 2010. Only the finalisation of refurbishments to the disabled access toilets remains before work at the school is finished.
- 10 Sep 2010 - Maribyrnong Primary P21
The works on the hall and major refurbishments were completed and handed over to the school on 3 August 2010. The BER Recognition Ceremony to celebrate the upgraded facilities will be held on 15 October 2010.
- 27 Jan 2011 - Maribyrnong Primary
The BER Recognition Ceremony to celebrate the upgraded facilities was held on 15 October 2010