01 Mar 2010 - Compacted base completed and waffle pods being installed in the lower part of the concrete slab
01 Mar 2010 - Lower concrete slab poured, waffle pods being installed for the higher level of the concrete slab
08 Jun 2010 - The ceiling is about to be installed in the new library. The ceiling panels, visible on the floor, have accoustic properties.
19 Jun 2010 - Inside the new building, accoustic wooden ceiling panels are being intalled in the library.
19 Jun 2010 - This is the lower level of the new building, which will house three General Learning Areas. A retractable wall will allow the area to be subdivided when desired.
28 Jun 2010 - The library office area, seen as a frame in the previous photo, is now ready for painting.
28 Jun 2010 - Work is progressing on the General Learning Areas. This large space will house three separate teaching spaces, and the area will be made more flexible with two retractable walls (still to be installed). Painting work will begin shortly.
26 Jul 2010 - Wide glass doors open from the new library, allowing abundant natural light into the building.
26 Jul 2010 - The large area containing three classrooms is made more flexible by the use of large, sliding wall dividers.
26 Jul 2010 - A view of the finished classroom area, showing one of the sliding dividers between the rooms that can be used to define and separate the teaching spaces. Each classroom has an interactive whiteboard. The building work has been completed and has been handed over to the school.
08 Aug 2010 - The new library building, taken on the day of handover to the school. This wall features a long series of floor to ceiling windows with coloured glass panes.
08 Aug 2010 - This image of the new library was taken on the day it was handed over to the school. It shows the accoustic panelled ceiling and the multi-coloured windows. The lighter coloured carpeting is used to delineate an area intended as a teaching space within the library.
25 Oct 2010 - The BER Recognition Ceremony celebrated the completion of the Miles Franklin Primary School P21 project on Friday 17 September 2010
25 Oct 2010 - The BER Recognition Ceremony celebrated the completion of the Miles Franklin Primary School P21 project on Friday 17 September 2010