Miles Franklin Primary School P21 Project News Archive
- 11 Feb 2010 - Miles Franklin Primary P21
Services connections to new site finished. Services diversions underway. Footing have been poured.
- 02 Mar 2010 - Miles Franklin Primary P21
Lower concret slab has been installed. Form work and waffell pods in place for the top slab
- 12 Apr 2010 - Miles Franklin Primary P21
Steelwork and brickwork are in progress
- 14 May 2010 - Miles Franklin Primary P21
Internal brickwork is in progress. Construction of a covered walkway beside the new building has commenced.
- 31 May 2010 - Miles Franklin Primary P21
The installation of roofing and of ducting for air-conditioning in the new library is underway. The three new classrooms will have evaporative cooling.
- 19 Jun 2010 - Miles Franklin Primary P21
The installation of roofing and air-conditioning has been completed. Currently, the library ceiling, which consists of accoustic wooden panels, is being installed, and framing has been constructed for a library office area.
- 28 Jun 2010 - Miles Franklin Primary P21
Work is progressing on the General Learning Areas, with the electrical fit-off and painting work due to begin shortly. In the library, the ceiling installation is finished and the office area has been clad with sheeting and is ready to paint.
- 26 Jul 2010 - Miles Franklin Primary P21
The building work has been completed and the three new classrooms and library were handed over to the school on 24 July 2010.
- 08 Aug 2010 - Miles Franklin Primary P21
A BER Recognition Ceremony to celebrate the completion of the new building will be held on 17 September 2010.
- 27 Jan 2011 - Miles Franklin P21
A BER Recognition Ceremony to celebrate the completion of the Miles Franklin P21 project was held on 17 September 2010