North Ainslie Primary P21 Project Gallery

23 Dec 2009 - Formworks and steel reinforcing preparation for pouring concrete slab

 

23 Dec 2009 - Pouring of the concrete slab for the new library

 

23 Dec 2009 - Concrete slab for the new library

 

11 Mar 2010 - Steel framework commenced for the new library

 

11 Mar 2010 - Installation of the steel framework for the new library

 

11 Mar 2010 - Sisaleton installation prior brickwork

 

11 Mar 2010 - Sisaleton installation prior brickwork

 

17 Mar 2010 - Installation of the roof to the new library

 

17 Mar 2010 - Brick work to the new library

 

17 Mar 2010 - Brick work to the new library

 

25 Mar 2010 - Brick work and window installation

 

25 Mar 2010 - Brick work and window installation

 

25 Mar 2010 - Installation of ducting for the cooling and ventilation system

 

25 Mar 2010 - Structural steel and partitioning underway as part of the new library construction

 

14 Apr 2010 - The link to create a hallway between the existing building and new library

 

14 Apr 2010 - Door and window framing

 

14 Apr 2010 - Ducting installation and services work underway

 

14 Apr 2010 - Commencement of ceiling work

 

13 May 2010 - Ceiling work in progress

 

13 May 2010 - Glass window installation progressing

 

27 May 2010 - Drywall and ceiling installation

 

27 May 2010 - Drywall and ceiling installation

 

27 May 2010 - Internal framework and glazing

 

15 Jun 2010 - Rainwater tanks will be connected to toilets

 

15 Jun 2010 - Ceiling and cabling nearly completed

 

15 Jun 2010 - Insulation installation completed

 

15 Jun 2010 - Drywall and ceiling installation continuing

 

15 Jun 2010 - Drywall and ceiling installation continuing

 

13 Jul 2010 - Underground services work in progress

 

13 Jul 2010 - Slab preparation for rainwater tank installation

 

13 Jul 2010 - Slab preparation for a COLA of the new library

 

13 Jul 2010 - The new circulation desk for the library

 

15 Jul 2010 - Internal wall painting in progress

 

15 Jul 2010 - Internal wall painting in progress

 

15 Jul 2010 - Rainwater tank installation and the link and new footpath between the new library and existing building

 

15 Jul 2010 - Front view of the new library

 

27 Jul 2010 - Slap preparation for footpath to the new library

 

27 Jul 2010 - Circulation desk of the new library

 

27 Jul 2010 - Internal view of the new library

 

27 Jul 2010 - Back view of the new library

 

27 Jul 2010 - Back view of the new library

 

09 Aug 2010 - Link between the new library and existing building

 

09 Aug 2010 - New concrete path from the new library to existing buildings

 

09 Aug 2010 - New concrete path from the new library to existing buildings

 

09 Aug 2010 - New concrete path from the new library to existing buildings

 

09 Aug 2010 - Rear entrance of the new library

 

09 Aug 2010 - Resource room of the new library

 

09 Aug 2010 - Installation of an interactive whiteboard to a teaching area

 

09 Aug 2010 - Circulation desk

 

09 Aug 2010 - An office behind the circulation desk

 

09 Aug 2010 - Front entrance doors of the new library

 

09 Aug 2010 - Computer station area

 

09 Aug 2010 - Computer station area

 

13 Aug 2010 - The computer station in the library

 

13 Aug 2010 - Library shelving

 

21 Sep 2010 - Old library prior to refurbishment

 

21 Sep 2010 - Newly refurbished double classroom

 

21 Sep 2010 - New carpet, joinery, computer station and student bag area

 

21 Sep 2010 - New wet area in the refurbished double classroom

 

30 Sep 2010 - New carpet and paint to the corridor to the new refurbished classroom

 

30 Sep 2010 - New furniture and IWB installation to the refurbished classroom

 

30 Sep 2010 - Student bag area in the refurbished classroom

 

30 Sep 2010 - New floor, paint, blind and lighting arrangement to the refurbished classroom

 

30 Sep 2010 - Wet area in the refurbished classroom

 

30 Sep 2010 - Wet area in the refurbished classroom

 

30 Sep 2010 - Refurbished classroom

 

10 Nov 2010 - View of the back of the new library building

 

10 Nov 2010 - The back of the new library building

 

10 Nov 2010 - New access path connecting the new library to the existing buildings

 

10 Nov 2010 - The front entrance of the new library

 

10 Nov 2010 - The front entrance of the new library

 

10 Dec 2010 - The BER Recognition Ceremony held on 03 December 2010 to celebrate the completion of the North Ainslie Primary School P21 project

 

10 Dec 2010 - An image from the BER Recognition Ceremony held at North Ainslie Primary School