16 Nov 2009 - Start of construction

23 Dec 2009 - Formworks and steel reinforcing preparation for pouring concrete slab

23 Dec 2009 - Concrete slab for the new multipurpose classrooms

23 Dec 2009 - Concrete slab for the new multipurpose classrooms

18 Feb 2010 - Steel works commenced on site of the multipurpose building

18 Feb 2010 - Steel framework being installed

18 Feb 2010 - Timber framing being installed

18 Feb 2010 - Timber framing completed

15 Mar 2010 - Preparation for brick cladding

15 Mar 2010 - Start of brick work

15 Mar 2010 - Steelwork for the new shadestructure

15 Mar 2010 - Steelwork for the new shadestructure

25 Mar 2010 - Brick cladding

25 Mar 2010 - Render to brickworks

25 Mar 2010 - Render to brickworks

25 Mar 2010 - Internal wall linings

08 Apr 2010 - Shade structure work completed

08 Apr 2010 - Internal framing and services works progressing

08 Apr 2010 - Internal framing and services works progressing

13 Apr 2010 - Rendering completion

13 Apr 2010 - Rendering completion

27 Apr 2010 - External painting

27 Apr 2010 - External painting

27 Apr 2010 - Internal wall and insulation work underway

27 Apr 2010 - Ceiling and lighting work progressing

24 May 2010 - Completed internal painting

24 May 2010 - Installation of light fittings

24 May 2010 - Joinery installation progressing

08 Jun 2010 - Softfall installed under shade structure

08 Jun 2010 - Rainwater tanks will be connected to toilets

08 Jun 2010 - Kitchenette works progressing

08 Jun 2010 - Front view of the new multipurpose building

08 Jun 2010 - View of the front entrance of the completed multipurpose building on the handover date, June 4, 2010

08 Jun 2010 - Front entrance of the multipurpose building

08 Jun 2010 - Outdoor learning area

08 Jun 2010 - Outdoor learning area

08 Jun 2010 - Outdoor learning area

08 Jun 2010 - Entry sliding doors

08 Jun 2010 - Entry sliding doors

08 Jun 2010 - Multipurpose hall

08 Jun 2010 - Multipurpose hall

08 Jun 2010 - Multipurpose hall

08 Jun 2010 - Classroom 1

08 Jun 2010 - Classroom 2

08 Jun 2010 - Student bag storage

08 Jun 2010 - Classroom storeroom

08 Jun 2010 - Wet area in the multipurpose room for art and craft

08 Jun 2010 - ESD feature: night purging

08 Jun 2010 - Student toilets

08 Jun 2010 - Rainwater tanks connected to toilets

08 Jun 2010 - Outdoor learning area

08 Jun 2010 - Outdoor learning area

08 Jun 2010 - Outdoor learning area

28 Jul 2010 - the new multipurpose classrooms

28 Jul 2010 - the new multipurpose classrooms

28 Jul 2010 - The new multipurpose classrooms

10 Aug 2010 - An image from the BER Recognition Ceremony held at the O'Connor Cooperative School on Friday, 6 August 2010.

10 Aug 2010 - An image from the BER Recognition Ceremony held at the O'Connor Cooperative School on Friday, 6 August 2010.

10 Aug 2010 - An image from the BER Recognition Ceremony held at the O'Connor Cooperative School on Friday, 6 August 2010.

10 Aug 2010 - An image from the BER Recognition Ceremony held at the O'Connor Cooperative School on Friday, 6 August 2010. All above images include students from the school with the Minister for Education & Training Mr Andrew Barr MLA, Senator Kate Lundy and the school Principal Ms Margaret May.

09 Oct 2009 - Demolition of old building at O'Connor Co-operative School

09 Nov 2009 - Demolition of old building

09 Nov 2009 - Site for a new building

09 Nov 2009 - Slab preparation