Palmerston District Primary P21 Project Gallery
31 May 2010 - The site has been levelled and cleared to prepare for the construction of the new multipurpose building. When completed, the building will include two new classrooms, a practical activities area and student facilities.
28 Jun 2010 - During curing time for the footings, work has been carried out on plumbing and drainage connections.
15 Jul 2010 - Reinforcing mesh being put in place in preparation for the construction of the slab for the new building. Despite wet weather(evident from the photograph)it is hoped the slab will be poured during the next week.
09 Aug 2010 - The slab for the building has been poured, and is being marked out in preparation for the beginning of structural steel erection, which is due to begin this week.
25 Aug 2010 - Internal blockwork walls are being constructed to form the classrooms. Blockwork is expected to continue for about the next three weeks. These walls will be panelled on completion.
29 Sep 2010 - An image of the new multipurpose building, which has been located next to an existing shade structure for convenient access.
29 Sep 2010 - With work still proceeding on the external walls, scaffolding is in place ready for the installation of panelling to the upper wall.
26 Nov 2010 - Completion of installation of hall ceiling, windows and louvers. Internal painting underway
20 Jan 2011 - Painting completed. joinery, carpet and interactive whiteboard installed in learning support unit