›› Site map    ›› Accessibility    ›› Languages    ›› Contact Us

About Us

Palmerston District Primary P21 Project Gallery

31 May 2010 - The site has been levelled and cleared to prepare for the construction of the new multipurpose building. When completed, the building will include two new classrooms, a practical activities area and student facilities.

 

07 Jun 2010 - Trenching for services connection is underway.

 

19 Jun 2010 - The footings for the new building have been poured.

 

28 Jun 2010 - During curing time for the footings, work has been carried out on plumbing and drainage connections.

 

15 Jul 2010 - Reinforcing mesh being put in place in preparation for the construction of the slab for the new building. Despite wet weather(evident from the photograph)it is hoped the slab will be poured during the next week.

 

09 Aug 2010 - The slab for the building has been poured, and is being marked out in preparation for the beginning of structural steel erection, which is due to begin this week.

 

25 Aug 2010 - The structural steel frame is being erected for the new multipurpose building.

 

25 Aug 2010 - Internal blockwork walls are being constructed to form the classrooms. Blockwork is expected to continue for about the next three weeks. These walls will be panelled on completion.

 

29 Sep 2010 - An image of the new multipurpose building, which has been located next to an existing shade structure for convenient access.

 

29 Sep 2010 - With work still proceeding on the external walls, scaffolding is in place ready for the installation of panelling to the upper wall.

 

26 Nov 2010 - Joinery installation in progress

 

26 Nov 2010 - Completion of installation of hall ceiling, windows and louvers. Internal painting underway

 

26 Nov 2010 - Door and window installation to the new classroom building

 

20 Jan 2011 - Back of the practical activities area nearing completion

 

20 Jan 2011 - Coloured board in external play area for chess and other games

 

20 Jan 2011 - Benches installed in external play area

 

20 Jan 2011 - Aluminium panels being installed on multipurpose building

 

20 Jan 2011 - Installation of aluminium panels on multipurpose building nearing completion

 

20 Jan 2011 - Multipurpose building with panels installed

 

20 Jan 2011 - Tiles painted and joinery installed in toilet

 

20 Jan 2011 - Inside of multipurpose room nearing completion

 

20 Jan 2011 - Painting completed in multipurpose building

 

20 Jan 2011 - Painting finished and joinery installed in multipurpose room

 

20 Jan 2011 - Painting completed and joinery installed in practical activities room

 

20 Jan 2011 - Painting completed. joinery, carpet and interactive whiteboard installed in learning support unit

 

11 Mar 2011 - Completion of the multipurpose building

 

11 Mar 2011 - Front entrance of the multipurpose building

 

11 Mar 2011 - Entrance of the multipurpose hall