23 Feb 2010 - Survey site and building setout for construction of a new multipurpose building

23 Feb 2010 - Excavation for piers and footings, pouring piers

23 Feb 2010 - pouring footings

23 Feb 2010 - Pouring footings

15 Mar 2010 - Compact fill for slab

15 Mar 2010 - Import fill for slab

15 Mar 2010 - Import fill for slab

17 Mar 2010 - Slab pour preparation work

17 Mar 2010 - Slab pour preparation work

17 Mar 2010 - Slab pour preparation work

17 Mar 2010 - Slab pour preparation work

26 Mar 2010 - Formwork and steel reinforcement for concrete slab pouring

26 Mar 2010 - Concrete slab pouring

26 Mar 2010 - Concrete slab pouring

26 Mar 2010 - Concrete slab pouring

26 Mar 2010 - Concrete slab pouring

26 Mar 2010 - completed floor slab

26 Mar 2010 - completed floor slab

21 Apr 2010 - Delivery of structural steel on site

21 Apr 2010 - Commencement of structural steel installation

21 Apr 2010 - Structural steel being installed

21 Apr 2010 - Structural steel being installed

21 Apr 2010 - Structural steel being installed

12 May 2010 - Commencement of roof work

12 May 2010 - Covered walkway to the new multipurpose hall and existing building

02 Jun 2010 - Commencement of internal framework for foyer

02 Jun 2010 - Cabling underway

02 Jun 2010 - Cabling underway

02 Jun 2010 - Walkway along the new general purpose hall

15 Jun 2010 - Continuation of internal frame installation for drywalls

15 Jun 2010 - Ceiling grid installation

25 Jun 2010 - Continuation of internal framework

25 Jun 2010 - Roof insulation

15 Jul 2010 - Internal wall painting in progress

27 Jul 2010 - Internal wall installation in progress

27 Jul 2010 - Installation of a stage to the new general purpose hall

27 Jul 2010 - Ceiling installation in progress

09 Aug 2010 - Continuation of installation of a stage to the new multipurpose hall

09 Aug 2010 - Installation of high level windows in progress

09 Aug 2010 - Installation of high level windows in progress

08 Sep 2010 - Heater installation to the new multipurpose hall

08 Sep 2010 - Heater installation to the new multipurpose hall

08 Sep 2010 - Stage installation in progress

08 Sep 2010 - Wheelchair lift installation to the stage

08 Sep 2010 - Wheelchair lift installation to the stage

08 Sep 2010 - Front view of the new multipurpose building

08 Sep 2010 - Front view of the new multipurpose building

08 Sep 2010 - Covered link between the new multipurpose building and the existing building

08 Sep 2010 - External louvered sun shade for the library

29 Sep 2010 - Front view of the new general purpose hall

29 Sep 2010 - New toilets in the general purpose hall

29 Sep 2010 - Completion of the hall floor

14 Oct 2010 - Access path linking the new multipurpose building to existing buildings

14 Oct 2010 - Access path linking the new multipurpose building to existing buildings

28 Oct 2010 - Completion of access path around the the new multipurpose building

28 Oct 2010 - The new multipurpose building is connected to the existing building by stairs and a disable lift

28 Oct 2010 - The new multipurpose building is connected to the existing building by stairs and a disable lift

28 Oct 2010 - Commencement of line marking for the new hall floor

28 Oct 2010 - Audiovisual installation to the new multipurpose hall

28 Oct 2010 - Curtain installation to the hall stage

10 Dec 2010 - Completion of the new multipurpose hall

10 Dec 2010 - Completion of the new multipurpose hall

10 Dec 2010 - Completion of the new multipurpose hall

10 Dec 2010 - The BER Recognition Ceremony held on 26 November 2010 to celebrate the completion of the Red Hill Primary School P21 project

10 Dec 2010 - An image from the BER Recognition Ceremony held at Red Hill Primary School