  • 25 Jan 2010 - Richardson Primary P21

Richardson Primary School P21 project - demolition work is in progress for the Library and classroom. Refurbishment of the North and Western toilets is in fitout phase.

  • 26 Feb 2010 - Richardson Primary P21

New northern boys and girls toilets and disabled toilets completed.

  • 09 Mar 2010 - Richardson Primary School P21

New joinery has been installed in the Library office area. Carpet in Library has been laid.

  • 15 Mar 2010 - Richardson Primary School P21

Library - Joinery installed for computers and loans area. Balistrade and stair hand rails being installed, carpet has been laid, library mobile shelving has arrived. Data cabling being installed. Kakadu - preparation for steel works & construction of toilet walls in progress.

  • 19 Mar 2010 - Richardson Primary School P21

LIBRARY - All fixed shelving has been installed, Loan counter in progress of being installed, ducts painted. KAKADU Classrooms - Demolition is continuing, steel preparation installation underway, internal walls removed, and the toilet wall has been extended.

  • 09 Apr 2010 - Richardson Primary School P21

Kakadu toilets construction underway. Steel work currently being installed for classrooms at Kakadu

  • 20 Apr 2010 - Richardson Primary School P21

Insulation and electric/plumbing roughins and ceiling gyprock complete for Kakadu room. Walls under construction. Southern toilets demolition underway.

  • 04 May 2010 - Richardson Primary School P21

Joinery, plaster and painting complete to the Classroom's. Bubblers have been completed.

  • 13 May 2010 - Richardson Primary School P21

Demolition of southern toilets complete. Works in the Kakadu room is nearing completion. New walls installed for entry and dividing classroom hallway.

  • 18 May 2010 - Richardson Primary School P21

Tiling is in progress to the southern toilets.

  • 18 May 2010 - Richardson Primary School P21

Kakadu classroom joinery has been installed.

  • 27 May 2010 - Richardson Primary School P21

Tiling is progressing well in the southern area student toilets.

  • 27 May 2010 - Richardson Primary School P21

Painting is progressing and the joinery is being installed for the Kakadu classroom.

  • 16 Jul 2010 - Richardson Primary School P21

The partial relocation of the boundary fence around the play equipment has been completed.

  • 27 Jan 2011 - Richardson Primary P21

The BER Recognition Ceremony was held on 06 August 2010 to celebrate the completion of the Richardson Primary School P21 project