23 Feb 2010 - Multipurpose room guttered

23 Feb 2010 - Hallstore services capped

23 Feb 2010 - Gyprock and plastering underway in Multipurpose / Hall Store room area

08 Apr 2010 - Demolition of classroom 11 commenced.

09 Apr 2010 - Demolition of classroom 11 complete.

09 Apr 2010 - Classroom 9 prior to refubishment.

09 Apr 2010 - Demolition of classroom 9 prior to refurbishment.

09 Apr 2010 - Classroom 10 prior to demolition

09 Apr 2010 - Classroom 10 demolition complete prior to refurbishment

09 Apr 2010 - Painting underway in the Multipurpose Room.

09 Apr 2010 - Electrical works nearing completion.

09 Apr 2010 - Multipurpose room entry complete.

09 Apr 2010 - Completion of Kitchen area in the Multipurpose room.

19 Apr 2010 - Ceiling grid system being installed in classroom.

19 Apr 2010 - Library prior to demolition.

19 Apr 2010 - Demolition of Library in progress.

19 Apr 2010 - Ducting system being installed.

19 Apr 2010 - Walls in the classroom being installed.

23 Apr 2010 - Library demolition completed. Ceiling grids are being installed.

23 Apr 2010 - Classroom ceiling panels have been installed. The electrical and data installed.

23 Apr 2010 - The doors and window frames have been installed to classroom.

03 May 2010 - Library workroom construction complete.

04 May 2010 - Classroom joinery, plaster and painting complete.

04 May 2010 - Classroom joinery, plaster and painting completed. The carpet is being laid.

11 May 2010 - Refurbishment of Library painting nearing completion.

11 May 2010 - Refurbishment of Classrooms has been completed.

11 May 2010 - Construction of new dividing classroom wall and hallway refurbishment complete.

25 May 2010 - Construction of the Library loans desk and storage has been completed.

26 May 2010 - Classroom demolition completed and installation of ceiling grids are progressing.

26 May 2010 - Classroom demolition completed. Ceiling grid being installed.

26 May 2010 - Demolition of the wet area completed.

23 Jul 2010 - Classroom refurbishment progressing with wall and ceiling linings completed.

23 Jul 2010 - Painting in progress for the classroom refurbishment.

23 Jul 2010 - Painting completed and data has been installed in the computer lab.

23 Jul 2010 - Vinyl has been laid and the installation of joinery has commenced for the wet area.

23 Jul 2010 - Carpet has been laid in the computer lab.

23 Jul 2010 - Computer Lab refurbishment is completed.

23 Jul 2010 - One of the wet areas Prior to demolition.

23 Jul 2010 - Classroom prior to refurbishment.

23 Jul 2010 - Demolition completed, with ceiling grids installed.

23 Jul 2010 - Demolition of wet area in progress.

23 Jul 2010 - Ramp and class area prior to demolition.

23 Jul 2010 - Demolition in progress prior to refurbishment.

20 Jan 2011 - Refurbished hallways and classrooms

20 Jan 2011 - Classroom ready for installation of electronic whiteboard

20 Jan 2011 - Electronic whiteboard installed in classroom

20 Jan 2011 - Joinery, projector, and electronic whiteboard installed in classroom

20 Jan 2011 - Refurbishment of canteen in progress

20 Jan 2011 - Painting near complete on refurbished canteen

11 Mar 2011 - completion of internal canteen servery

11 Mar 2011 - Completion of canteen refurbishment

11 Mar 2011 - Refurbished multipurpose room

11 Mar 2011 - Completion of classroom refurbishment

11 Mar 2011 - IWB installed to the refurbished classroom

11 Mar 2011 - Completion of wet area refurbishment

11 Mar 2011 - Completion of music performance area refurbishment

11 Mar 2011 - Refurbished computer lab

11 Mar 2011 - Refurbished library

11 Mar 2011 - Completion of library refurbishment

11 Mar 2011 - The BER Recognition Ceremony to celebrate the completion of the BER works

11 Mar 2011 - Minister Ms Joy Burch MLA addressing in the BER Recognition Ceremony