
15 Mar 2010 - Site prior to excavation

15 Mar 2010 - Site after building demolished.

24 Mar 2010 - Site fully cleared.

24 Mar 2010 - Footings to upper section of new building complete

06 Apr 2010 - The lower section of the Multipurpose building concrete slab has been laid.

16 Apr 2010 - Concrete slab has been laid for the upper section of the Multipurpose building.

27 Apr 2010 - Footings for the walkway connecting the building to the school is complete.

11 May 2010 - Retaining walls to the upper section of the new Multipurpose building are being constructed.

22 Jun 2010 - Structural steel is being erected to the upper concrete section slab.

25 Jun 2010 - Structural steel for the upper section of the Multipurpose building has been erected and purlins are being attached.

09 Jul 2010 - Purlins being attached to the framework of the Multipurpose building.

09 Jul 2010 - Crane lifting steel framework in place to the Multipurpose building.

09 Jul 2010 - Framework errected to the upper section of the Multipurpose building.

09 Jul 2010 - Steelwork progressing to the Multipurpose building.

21 Jan 2011 - Insulation installed in preparation for external cladding

21 Jan 2011 - Interior brickwork nearing completion in multipurpose hall

21 Jan 2011 - Grids for ceiling and HVAC installed in multipurpose building

21 Jan 2011 - Installation of louvres and construction of external wall underway

21 Jan 2011 - External cladding in progress

21 Jan 2011 - Installation of doors and windows of multipurpose building nearing completion

21 Jan 2011 - Preparation for environmental kitchen

21 Jan 2011 - Preparation for environmental kitchen in progress

21 Jan 2011 - Floor coverings installed in multipurpose room

21 Jan 2011 - External basins installed on environmental building

21 Jan 2011 - Completed front entry and ramp

21 Jan 2011 - Construction of covered walkway and ramp

21 Jan 2011 - Entrance from covered walkway completed

21 Jan 2011 - Covered walkway completed

21 Jan 2011 - Interior of multipurpose room completed

21 Jan 2011 - Interior of multipurpose hall completed

21 Jan 2011 - Interior of environmental learning centre completed

21 Jan 2011 - Recognition Ceremony took place 10th December 2010