Wanniassa Hills Primary School P21 Project News Archive

  • 25 Jan 2010 - Wanniassa Hills Primary P21

Wanniassa Hills Primary P21 project - awaiting electrical/power work to be completed by ACTewAGL before demolition of the Health Centre

  • 26 Feb 2010 - Wanniassa Hills Primary School P21

Demolition of the Health Centre is complete and the area has been cleared.

  • 09 Mar 2010 - Wanniassa Hills Primary School P21

Site for new multipurpose building cleared.

  • 12 Mar 2010 - Wanniassa Hills Primary P21

Site is fully cleared.

  • 19 Mar 2010 - Wanniassa Hills Primary School P21

Site fully cleared. Bulk excavation completed. Detailed excavation is under way and some of the footings to the upper part of the new building are complete.

  • 29 Mar 2010 - Wanniassa Hills Primary P21

Reinforcement and the waterproof membrane are in place awaiting the laying of the concrete slab. Further plumbing rough-in is taking place.

  • 09 Apr 2010 - Wanniassa Hills Primary School P21

All plumbing has been roughed in. The lower section of the concrete slab has been laid. Preparation of the ground prior to the laying of the concrete slab to the upper section is progressing.

  • 19 Apr 2010 - Wanniassa Hills Primary School P21

Both concrete slabs have been laid. Civil works are progressing for the new multipurpose building. The footings are being dug for the connecting pathway to the main school

  • 13 May 2010 - Wanniassa Hills Primary School P21

The retaining walls and the path to the northern side of the Multipurpose building are being built.

  • 18 May 2010 - Wanniassa Hills Primary School P21

Retaining walls to the upper section of the new Multipurpose building and the path completed.

  • 27 May 2010 - Wanniassa Hills Priamry School P21

There has been a delay in the supply of structural steel to the site, work has not been able to progress.

  • 15 Jul 2010 - Wanniassa Hills Primary School P21

Steel work has been erected to the lower slab. Wall formwork has been added to the upper slab and bricklaying has commenced.

  • 21 Jan 2011 - Wanniassa Hills Primary P21

Project completed and Recognition Ceremony held on 10th December 2010