24 Feb 2010 - Basketball courts prior to demolition

24 Feb 2010 - Demolition of basketball courts looking away from school hall towards site sheds and playground

24 Feb 2010 - Demolition of basketball courts looking back towards school hall

24 Feb 2010 - Floor tiles, partitions and pans removed from toilets as part of refurbishments

24 Feb 2010 - Demolition of toilets including removal of floor tiles

24 Feb 2010 - Toilets demolished and clean ready for construction

24 Feb 2010 - Partial construction of back wall of toilets to form store room wall

24 Feb 2010 - Brick wall to form store room nearing completion

24 Feb 2010 - Brick wall in adjacent toilets ready for installation of new ceiling

24 Mar 2010 - Footings for COLA poured.

24 Mar 2010 - Painting complete and carpet laid in Green Pod.

24 Mar 2010 - Painting in progress in Hall

07 Apr 2010 - Structural steel for Assembly area has been erected.

07 Apr 2010 - Tiling is progressing in the toilets.

16 Apr 2010 - All structural steel for the Assembly area and purlins have been constructed.

16 Apr 2010 - Painting is complete and the carpet is now being laid to the Red teaching pod.

27 Apr 2010 - Roof for the COLA is nearing completion.

27 Apr 2010 - Water tanks have been delivered and ready for installation.

04 May 2010 - The roof is complete and the roof lining is being installed.

04 May 2010 - Structural work, tiling and painting has been completed in the Girls toilets.

04 May 2010 - Plumbing work is progressing in the Boys toilets.

11 May 2010 - The roof and roof lining to the Place of Assembly has been fully installed.

11 May 2010 - The plumbing and joinery fit-out is progressing in both girls and boys toilets.

18 May 2010 - Electrical fit out to the Place of Assembly is progressing.

18 May 2010 - Construction of both girls and boys toilets are nearing completion.

25 May 2010 - Construction of the Place of Assembly is complete.

25 May 2010 - Installation of the Comcork flooring to the hall is nearing completion.

25 May 2010 - Completion of the tank stands awaiting placement of water tanks.

22 Jun 2010 - Construction of the individual practise room has commenced in the Purple Pod.

22 Jun 2010 - Tiling in the second set of toilets is progressing.

25 Jun 2010 - Wall lining of the practice rooms in the Purple pod has been complete.

25 Jun 2010 - Tiling in the second set of toilets is nearing completion.

25 Jun 2010 - Demolition for the disabled toilets has been completed.

09 Jul 2010 - The concrete slab for the disabled toilet.

09 Jul 2010 - Practice room in the purple pod has been completed.

09 Jul 2010 - Joinery for student music instrument's completed in the Purple pod.

09 Jul 2010 - Painting completed in classroom showing the entry to practice room.

09 Jul 2010 - Brickwork nearing completion for the disabled toilet.

09 Jul 2010 - Refurbishment of toilets is completed.

09 Jul 2010 - Purple pod practice rooms completed.

09 Jul 2010 - Construction of one of the small COLA has commenced.

09 Jul 2010 - Construction of a small COLA has commenced.

14 Jan 2011 - Completion the small COLA with benches

14 Jan 2011 - Completion of small COLA over sand pit

14 Jan 2011 - Completion of the new floor of the hall

14 Jan 2011 - Completion of new Comcork floor in the hall

14 Jan 2011 - The BER Recognition Ceremony held on 30 July 2010 to celebrate the completion of the Wanniassa School P21 project

14 Jan 2011 - An image form the BER Recognition Ceremony held at Wanniassa School