01 Mar 2010 - Building perimeter footing installed and block works commencing

01 Mar 2010 - Low level block work in place in preparation for form work for the concrete slab

01 Mar 2010 - Footing in place for the interior walls of the building

01 Mar 2010 - Form work and reinforcing steel in place in preparation for the pouring of the concrete slab

01 Mar 2010 - Concrete slab for the new multi purpose building completed

01 Mar 2010 - Steel framework being installed

01 Mar 2010 - Steel framework being installed

01 Mar 2010 - Steel framework being installed

26 Mar 2010 - Brickwork underway on multipurpose building

26 Mar 2010 - Structural steel over outdoor multipurpose area

26 Mar 2010 - Brickwork and window frames on learning spaces in multipurpose building

21 Apr 2010 - Blockwork for the Multipurpose building in nearing completion.

21 Apr 2010 - Main structural steel framework complete with purlins for the multpurpose building.

21 Apr 2010 - Scaffolding erected ready for installation of roof sheeting to the outdoor area of the Multipurpose building.

21 Apr 2010 - External blockwork completed for the Multipurpose building.

21 Apr 2010 - Mesh installed to accept the insulation and roof sheeting.

06 May 2010 - Insulation and roof sheeting installed and blockwork close to completion

06 May 2010 - Internal blockwork completed and electrical rough in for the new multipurpose building

20 May 2010 - View of the outdoor multipurpose area

20 May 2010 - Window frames have been installed

07 Jun 2010 - Glazing has been installed in the high triangular space above the doorway to allow natural light to enter.

07 Jun 2010 - The glazing from the previous photo shown from the outside of the building.

19 Jun 2010 - The internal fit-out of the new building is proceding. Here, gas heating has been installed in the Shared Learning Area.

29 Jun 2010 - The exterior of the building with its coloured feature panels can be seen clearly for the first time now that the scaffolding has been taken down. The wide eaves are an environmental design feature that will shade the windows from high angle summer sun, while still letting sunlight into the building in winter. The external cladding has been completed.

26 Jul 2010 - Large, louvre-like sunshades have been installed to help cool the building in summer. While keeping out direct sunlight, they will still allow unimpeded natural ventilation.

26 Jul 2010 - Paving being constructed along the side of the new building.

26 Jul 2010 - This image shows the large roofed area, intended for multipurpose use, which connects to the indoor teaching area. The glass wall between the indoor and outdoor spaces can be opened completely out of the way.

09 Aug 2010 - An outdoor stage area, which opens into the new building, is being constructed.

09 Aug 2010 - An outdoor seating area.

09 Aug 2010 - A new disabled access toilet and shower facility has been completed.

09 Aug 2010 - Internal painting work being carried out, in the distinctive white and yellow colour scheme used throughout the new building.

09 Aug 2010 - The completed kitchenette in the new multipurpose building.

25 Aug 2010 - New toilet facilities have been completed.

25 Aug 2010 - This image of the completed building shows how the huge "hanger-style" glass door can open completely out of the way to give unimpeded access between the interior of the building and the roofed outdoor multipurpose space.

25 Aug 2010 - A close-up view of the door, showing how it folds out of the way.

25 Aug 2010 - A view of the completed shared learning area from the inside, with the door closed.

25 Aug 2010 - The new classrooms have been completed and are ready for use. The building was handed over to the school on 20 August 2010.

24 Jan 2011 - Completed new classroom

24 Jan 2011 - Education Minister Andrew Barr addressing the crowd at the BER Recognition Ceremony for Weetangera Primary, held on 3 September 2010