- 21 Jan 2010 - Yarralumla Primary P21
Yarralumla Primary School - P21 bulk excavation completed, relocation of in ground services to be completed this week.
- 11 Feb 2010 - Yarralumla Primary P21
Detailed excavation started.
- 17 Jun 2010 - Yarralumla Primary P21
Yarralumla Primary P21 project – Roof sheeting completed, smartfix cladding completed, perimeter scaffolding removed. Dry wall installation continuing
- 10 Sep 2010 - Yarralumla Primary P21
Construction works are completed and the building was handed back to the school today, the old library will be relocated into the new space over the next week and external works will be completed by the end of the month.
- 06 Oct 2010 - Yarralumla Primary P21
Construction of the new library completed with landscaping consolidation. The library handed over to the school. A Recognition Ceremony to celebrate the completion of the Yarralumla Primary School P21 project will be held on October 22, 2010 at 10:30 am.
- 27 Jan 2011 - Yarralumla Primary School P21
A Recognition Ceremony to celebrate the completion of the Yarralumla Primary School P21 project was held on October 22, 2010