29 Mar 2010 - Site preparation for construction of new classrooms and multipurpose spaces

29 Mar 2010 - Bulk earth works and excavation for new P21 Building

29 Mar 2010 - Footing for new P21 Building

29 Mar 2010 - Footing for new P21 Building

09 Apr 2010 - Commencement of base block work for exterior walls

09 Apr 2010 - Commencement of base block work for exterior walls

14 Apr 2010 - Completion of base block work for exterior walls

19 May 2010 - Preparation for ground services

19 May 2010 - Formwork and steel reinforcement for concrete slab pouring

19 May 2010 - Formwork and steel reinforcement for concrete slab pouring

28 May 2010 - Completed concrete slab to new multipurpose building, including office, kitchen and toilets blocks, two classrooms and multipurpose space

28 May 2010 - Completed concrete slab and base blockwork

28 May 2010 - Formwork and steel reinforcement for concrete slab pouring to classroom 1 & 2

11 Jun 2010 - Continuation of slab for two new classrooms

11 Jun 2010 - Continuation of slab for two new classrooms

21 Jun 2010 - Continuation of underground services work

21 Jun 2010 - Commencement of blockwork

21 Jun 2010 - Commencement of blockwork to multipurpose space

02 Jul 2010 - Commencement of blockwork to multipurpose space

02 Jul 2010 - Commencement of blockwork to multipurpose space

14 Jul 2010 - Installation of structural steel and commencement of blockwork

14 Jul 2010 - Installation of structural steel and commencement of blockwork

03 Aug 2010 - Blockwork in progress

05 Aug 2010 - Completion of Blockwork

05 Aug 2010 - Installation of structural steel in progress

05 Aug 2010 - Installation of structural steel in progress

16 Aug 2010 - Completion of structural steel installation

16 Aug 2010 - Completion of structural steel installation

01 Sep 2010 - Commencement of wall redering

01 Sep 2010 - Commencement of wall rendering

13 Sep 2010 - Structural steel for roof sheeting

13 Sep 2010 - Scaffolding for construction of roof and ceiling

16 Sep 2010 - Continuation of Render to external blockwork

16 Sep 2010 - Roof sheeting in progress

01 Oct 2010 - Completion of external wall rendering, with roof sheet to follow

01 Oct 2010 - Preparation for ceiling installation

01 Oct 2010 - Internal wall framing in progress

12 Oct 2010 - Installation of ceiling grid in progress

22 Oct 2010 - Construction of internal walls and suspended ceiling

22 Oct 2010 - Cladding of upper walls, within environmental courtyard

02 Feb 2011 - Courtyard under construction

02 Feb 2011 - Construction of covered outdoor learning area

02 Feb 2011 - Side entrance to new multipurpose hall

02 Feb 2011 - Kitchen within multipurpose hall

08 Mar 2011 - Finished kitchen within the multipurpose building

08 Mar 2011 - Completed multipurpose hall of the multipurpose building

08 Mar 2011 - The office in the multipurpose building

08 Mar 2011 - Installation of IWB in the multipurpose hall

08 Mar 2011 - Completion of the classroom in the multipurpose building

08 Mar 2011 - Side entrance to the completed multipurpose hall

08 Mar 2011 - Side view of the completed multipurpose hall

22 Mar 2011 - Classroom in the new multipurpose building

22 Mar 2011 - Another classroom in the new multipurpose building

22 Mar 2011 - The BER Recognition Ceremony held on 18 March 2011 to celebrate the completion of the Ainslie School BER project