Arawang Primary School P21 Project News Archive
- 22 Jan 2010 - Arawang Primary P21
Arawang Primary School p21 project - Library refurbishment completed. New building bulk excavation and civil workscompleted. Footing excavation and under slab hydraulics commenced this week.
- 25 Feb 2010 - Arawang Primary P21
Heavy rain has caused a delay of five days but the concrete slab has now been poured and the structural steelwork is due on site to commence erection on Monday 1st March.
- 15 Mar 2010 - Arawang Primary School P21
After the delay due to the recent rains erection of the structural steelwork has commenced.
- 19 Mar 2010 - Arawang Primary School P21
Erection of structural steelwork is complete. Roof purlins and top hat sections have been installed ready for roofing.
- 19 Apr 2010 - Arawang Primary School P21
structural steelwork, and roof purlins are completed. The insulation and roof sheeting now complete.
- 27 May 2010 - Arawang Primary School P21
Structural steel has been erected and the wall framing is complete.
- 15 Jul 2010 - Arawang Primary School P21
Internal blockwork complete, the isulation and windows instalation has commenced. External cladding has commenced to Multipurpose building and covered walkway.
- 25 Jan 2011 - Arawang Primary P21
The Recognition Ceremony to celebrate the completion of the Arawang Primary School was held on 22 October 2010