15 Mar 2010 - Site Accomodation

15 Mar 2010 - Site cleared for New Multi-purpose Building

15 Mar 2010 - Slab complete with structural steel

15 Mar 2010 - Steel work commenced

19 Mar 2010 - Erection of Structural steelwork is completed.

19 Mar 2010 - Multipurpose building ready for roofing to be installed.

07 Apr 2010 - Installation of metal roofing to multipurpose building completed.

27 May 2010 - Erection of Structural steel completed. Wall framing complete, and laying of blockwork is in progress.

27 May 2010 - External brickwork for the Multipurpose building has commenced.

06 Jul 2010 - Structural steel completed ready for the wall cladding in the Multipurpose building.

06 Jul 2010 - Blockwork completed. Insulation in place and the installation of windows commencing.

06 Jul 2010 - Internal walls and sheeting commencing for the covered walkway between the school and the Multipurpose building.

06 Jul 2010 - External cladding commencing to Multipurpose building and the covered walkway.

13 Sep 2010 - Operable window louvers for air fentilation being installed in the New Multipurpose building.

13 Sep 2010 - Insulation being installed, windows/glazing installed and gyprock in preogress for the Multipurpose building.

13 Sep 2010 - Cladding and yellow smartfix in progress for the Multipurpose building.

25 Jan 2011 - Brickwork completed on exterior of multipurpose building

25 Jan 2011 - Aluminium panels installation underway

25 Jan 2011 - Aluminium panels installation near completion

25 Jan 2011 - Brickwork completed (north-west view)

25 Jan 2011 - Installation of panels near completion

25 Jan 2011 - Installation of windows and external doors completed

25 Jan 2011 - Installation of cabling underway in multipurpose room

25 Jan 2011 - Insulation complete and construction of ceiling underway

25 Jan 2011 - Painting commenced in enclosed walkway

25 Jan 2011 - Louvres installed and painting underway in multipurpose room

25 Jan 2011 - Louvres and windows have been installed in classroom

25 Jan 2011 - Installation of joinery underway in classroom

25 Jan 2011 - Tiling completed and installation of joinery underway in toilet

25 Jan 2011 - Lights have been installed and painting near completion in classroom

25 Jan 2011 - Doors have been installed and painting near completion in enclosed walkway

25 Jan 2011 - Arrival of rainwater tanks to site

25 Jan 2011 - Installation of rainwater tanks underway

25 Jan 2011 - External gutters and facia being installed

25 Jan 2011 - Toilets completed in multipurpose building

25 Jan 2011 - Gas-radiant heaters installed in multipurpose room

25 Jan 2011 - Entrance to multipurpose room from covered walkway completed

25 Jan 2011 - Interactive whiteboard installed in classroom 1

25 Jan 2011 - Kitchen in multipurpose building completed

25 Jan 2011 - Classroom 1 in multipurpose building completed

25 Jan 2011 - Classroom 2 of multipurpose building completed

25 Jan 2011 - Interactive whiteboard installed in multipurpose room

25 Jan 2011 - Multipurpose room completed

25 Jan 2011 - Northwest view showing new rainwater tanks and fence

25 Jan 2011 - Completed multipurpose building

25 Jan 2011 - Completed multipurpose building

25 Jan 2011 - Completed multipurpose building

25 Jan 2011 - Recognition Ceremony underway

25 Jan 2011 - The Recognition Ceremony to celebrate the completion of the Arawang Primary School was held on 22 October 2010