Caroline Chisholm School P21 Project News Archive

  • 26 Feb 2010 - Caroline Chisholm School P21

Compacting fill works completed and the footings dug and steel work in place.

  • 09 Mar 2010 - Caroline Chisholm School P21

Construction commenced, compacting fill works completed. Footings laid and brick works commenced.

  • 15 Mar 2010 - Caroline Chisholm School P21

Construction commenced. Footings laid and completed for slab. Inground Hydraulics being laid.

  • 19 Mar 2010 - Caroline Chisholm Primary School P21

Hydraulics have been trenched in. Steel for the slab has arrived.

  • 01 Apr 2010 - Caroline Chisholm Primary School P21

Final Sketch Plans for Hall entry refurbishment finalised 31 March 2010.

  • 09 Apr 2010 - Caroline Chisholm School P21

Steelworks for the Multipurpose building is being erected. The design documentations is being finalised.

  • 15 Apr 2010 - Caroline Chisholm School P21

Steel is being erected for the Multipirpose Building.

  • 04 May 2010 - Caroline Chisholm School P21

The steelwork has been completed. The wall framing has commenced.

  • 13 May 2010 - Caroline Chisholm School P21

The timber frames are being erected to the Mutlipurpose building.

  • 18 May 2010 - Caroline Chisholm School P21

Windows have been installed to the new Multipurpose building.

  • 15 Jul 2010 - Caroline Chisholm School P21

Ventilation ducts have been fitted and the internal frames are nearing completion for the Multipurpose building.

  • 27 Jan 2011 - Caroline Chisholm School P21

A BER Recognition Ceremony to celebrate the completion of the Caroline Chisholm School P21 project will be held on the 25 February 2011