- 22 Jan 2010 - Chapman Primary School P21
Chapman Primary School P21 project - Under slab hydraulicsand new building slab completed. Relocation of services completed.Structural steel under manufacture and expected on site 22/2/2010
- 25 Feb 2010 - Chapman Primary School P21
Some delays have been experienced in the supply of structural steelwork but this is now expected in the week commencing 15th March.
- 19 Mar 2010 - Chapman Primary School P21
Library Building-Floor slab and services have been roughed in and completed. Structural steel has been delivered.
- 19 Apr 2010 - Chapman Primary School P21
Structural steel erection is nearing completion.
- 04 May 2010 - Chapman Primary School P21
The structural steel and roofing have been completed. The external cladding work has commenced.
- 27 May 2010 - Chapman Primary School P21
Breezeway wall cladding has been installed to the Library building.
- 16 Jul 2010 - Chapman Primary School P21
The roof installation is completed. The blockwork for the ramp is progressing.
- 24 Jan 2011 - Chapman Primary School P21
The BER Recognition Ceremony was held on 10 December 2010 to celebrate the completion of the Chapman Primary School P21 Project