Chapman Primary School P21 Project News Archive

  • 22 Jan 2010 - Chapman Primary School P21

Chapman Primary School P21 project - Under slab hydraulicsand new building slab completed. Relocation of services completed.Structural steel under manufacture and expected on site 22/2/2010

  • 25 Feb 2010 - Chapman Primary School P21

Some delays have been experienced in the supply of structural steelwork but this is now expected in the week commencing 15th March.

  • 19 Mar 2010 - Chapman Primary School P21

Library Building-Floor slab and services have been roughed in and completed. Structural steel has been delivered.

  • 19 Apr 2010 - Chapman Primary School P21

Structural steel erection is nearing completion.

  • 04 May 2010 - Chapman Primary School P21

The structural steel and roofing have been completed. The external cladding work has commenced.

  • 27 May 2010 - Chapman Primary School P21

Breezeway wall cladding has been installed to the Library building.

  • 16 Jul 2010 - Chapman Primary School P21

The roof installation is completed. The blockwork for the ramp is progressing.

  • 24 Jan 2011 - Chapman Primary School P21

The BER Recognition Ceremony was held on 10 December 2010 to celebrate the completion of the Chapman Primary School P21 Project