08 Feb 2010 - Hall prior to works being undertaken

08 Feb 2010 - Demolition of Shade Structure

08 Feb 2010 - Demolition of internal wall panelling, existing stage, ceiling, timber framing stripped and external hall wall

08 Feb 2010 - Relocated Shade Structure to the preschool site

15 Mar 2010 - Site prior to construction of Multipurpose building

15 Mar 2010 - Stage prior to demolition with floor lined to provide plant structure support.

15 Mar 2010 - Hall floor lined to provide plant structural support. View from stage

15 Mar 2010 - Canteen in Hall prior to demolition.

15 Mar 2010 - Demolition of canteen

15 Mar 2010 - Slab preparation for extension

15 Mar 2010 - Stage build is complete.

15 Mar 2010 - Demolition of Hall in progress

15 Mar 2010 - Demolition nearing completion

15 Mar 2010 - Footings for Hall extension

15 Mar 2010 - Scaffolding has been erected for end of the roof support.

30 Mar 2010 - Recycled timber cladding on bulk head stage being installed.

30 Mar 2010 - Concrete topping front entrance to Hall

07 Apr 2010 - Structural steel frame nearing completion.

19 Apr 2010 - Canteen timber framing works nearing completion.

19 Apr 2010 - Stage cladding nearing completion. Installation of storage area doors underway. Existing hall ceiling insulation and paint completed.

19 Apr 2010 - Tiling of toilets underway.

23 Apr 2010 - Scaffolding being constructed at the back of the Multipurpose Hall.

23 Apr 2010 - Wall panelling in the Hall entry commenced.

23 Apr 2010 - Tiling in the toilet area in the Hall nearing completion.

10 May 2010 - Roofing for the Extention of the Multipurpose hall in progress.

10 May 2010 - Timber wall pannelling to the front entrance complete.

10 May 2010 - Stairs for the stage installed.

17 May 2010 - Installation of Roof complete.

17 May 2010 - Timber wall pannelling for the front of the stage in the Multipurpose Hall is complete.

17 May 2010 - Construction of the Canteen awning is progressing.

25 May 2010 - Stage panelling nearing completion in the Multipurpose Hall.

25 May 2010 - Construction of the Canteen awning has been completed in the Multipurpose Hall.

25 May 2010 - The acoustic ceiling installation is in progress and the internal wood panelling is being installed to the wall at the rear end of the extension of the multipurpose Hall.

03 Jun 2010 - The installation of the stage panelling has been completed for the Multipirpose Hall.

03 Jun 2010 - Plastering of the Canteen walls and construction of the bulkhead for the servery in progress.

03 Jun 2010 - Painting underway at the end of the undercover area. Back of Hall and ceiling insulation in progres to the Multipurpose Hall.

03 Jun 2010 - Doors are being installed to the Multipurpose Hall.

15 Jun 2010 - Internal extension to the Multipurpose Hall painting completed, ceiling lining and insulation complete.

22 Jun 2010 - Floorboards are being laid in the Multipurpose Hall.

22 Jun 2010 - Water tanks have been deliveried awaiting installation.

22 Jun 2010 - Front counterweight doors installed to the Multipurpose Hall.

25 Jun 2010 - Sports storeroom joinery completed in the Multipurpose building.

07 Jul 2010 - Laying of the Hall floor is progressing.

07 Jul 2010 - Canteen joinery has been installed and the installation of the electrical services are progressing in the Multipurpose Hall extension.

07 Jul 2010 - Toilets have been completed in the Multipurpose Hall.

07 Jul 2010 - External posts for the covered walkway have been erected.

07 Jul 2010 - The external doors have been hung in the Multipurpose Hall.

07 Jul 2010 - The Vinyl has been laid to the entry to the Multipurpose Hall.

07 Jul 2010 - Pipe work installed for the Rainwater tank's.

07 Jul 2010 - Demolition of the Year 1/2 classroom has been completed.

07 Jul 2010 - Demolition of the Junior toilets has been completed.

24 Jan 2011 - Refurbished junior toilets

24 Jan 2011 - Completion of the Covered Outdoor Area at rear of extended hall

24 Jan 2011 - Completion of new bitumen in existing basketball court area

24 Jan 2011 - Completion of the refurbished canteen in the extended hall

24 Jan 2011 - Completed new canteen storeroom

24 Jan 2011 - Refurbished corridor in the hall

24 Jan 2011 - Refurbished disabled toilet in the hall

24 Jan 2011 - Extension of existing hall of the newly refurbished hall

24 Jan 2011 - New lighting and audio visual equipment

24 Jan 2011 - New stage of the multipurpose hall

24 Jan 2011 - Entry of the extended hall with view to operable bi-fold doors leading out to courtyard

24 Jan 2011 - First line marking in the multipurpose hall

24 Jan 2011 - The BER Recognition Ceremony to celebrate the completion of the Charles Conder Primary School P21 project

24 Jan 2011 - An image from the BER Recognition Ceremony held on 24 September 2010 at Charles Conder Primary School