Fadden Primary School P21 Project News Archive
- 22 Jan 2010 - Fadden Primary School P21
Fadden Primary School P21 project - Stage 1 refurbishment of audio visual room and hall toilet facilities 80% completed.
- 26 Feb 2010 - Fadden Primary School P21
Structural steel in place in Kuringai learning unit to support removal of vertical beam that is positioned in the middle of teaching space 1.
- 09 Mar 2010 - Fadden Primary School P21
All internal structural work is complete. Support room attached to wet area has been constructed.
- 12 Mar 2010 - Fadden Primary School P21
Some of the internal telescopic doors have been fitted and the data/electrical cabling is almost complete. New windows and doors are in the process of being fitted.
- 19 Mar 2010 - Fadden Primary School P21
All windows and doors have been installed. Electrical and data rough-in is complete. Tracks and wall cavities for sliding dividers have been fitted and joinery to accommodate IWB infrastructure has been completed. Gyprock installation nearing completion.
- 26 Mar 2010 - Fadden Primary School P21
Sheet gyprock installation completed. All internal sliding door tracks are installed and specialty areas such as for cleaning have been constructed. All mechanical services have been installed.
- 09 Apr 2010 - Fadden Primary School P21
Sheet gyprock being prepared for painting and infrastructure for IWBs have been installed. Joinery is being fitted and vents for mechanical services are being installed
- 09 Apr 2010 - Fadden Primary School P21
Installation of joinery is progressing and the painting of the teaching pod is nearing completion.
- 19 Apr 2010 - Fadden Primary School P21
All sliding glass partition walls have been fitted. Painting is progressing well in the teaching unit. Construction of the new cleaners room is complete.
- 04 May 2010 - Fadden Primary School P21
All Autex has been installed in classroom's. Joinery in the wet area has been installed.
- 13 May 2010 - Fadden Primary School P21
Construction work in the Kuringai classroom is completed.
- 27 May 2010 - Fadden Primary School P21
Demolition has commenced in the Murramurang learning pod.
- 15 Jul 2010 - Fadden Primary School P21
The wet area is complete, painting is nearing completion, the external doors have been fitted, and the joinery is progressing to the learning areas of the Murramarang Pod.
- 27 Jan 2011 - Fadden Primary School
A BER Recognition Ceremony to celebrate the completion of the Fadden Primary School P21 project will be held on 4 March 2011