Gilmore Primary School P21 Project News Archive

  • 25 Jan 2010 - Gilmore Primary School P21

Gilmore Primary School P21 project - Library fitout including new floor coverings, lighting and joinery underway.

  • 26 Feb 2010 - Gilmore Primary School P21

The Library is completed. Drywall installation is largely complete in Alison Lester learning unit. Joinery is being installed in bag room and wet area.

  • 09 Mar 2010 - Gilmore Primary School P21

Steel framework for the extension of the Alison Lester pod is constrcted.

  • 12 Mar 2010 - Gilmore Primary School P21

Internal structural changes are now complete and the joinery is being installed.

  • 19 Mar 2010 - Gilmore Primary School P21

Electrical rough-in and gyprock work complete. Painting nearing completion and extension of pod completed and incorporated into the rest of the teaching pod. Joinery has been installed in the wet area.

  • 29 Mar 2010 - Gilmore Primary School P21

All works in the Alison Lester teaching pod have been completed and handover has occurred. Staff, students and necessary resources will begin moving back into the pod immediately and demolition in the next pod, Jennie Baker, will commence.

  • 09 Apr 2010 - Gilmore Primary School P21

Staff and students have occupied the completed Alison Lester teaching pod. Demolition has commenced in the Jennie Baker teaching pod.

  • 19 Apr 2010 - Gilmore Primary School P21

Demolition in Jennie Baker teaching pod is completed. Preparation for painting is progressing and structural work in the pod is progressing. Slab has been laid outside to extend pod.

  • 04 May 2010 - Gilmore Primary School P21

Painting is nearing completion in the Jeannie Baker unit.

  • 13 May 2010 - Gilmore Primary School P21

Painting and the extension to the Jeannie Baker pod is completed. The joinery in the wet area is installed.

  • 18 May 2010 - Gilmore Primary School P21

Construction is complete in the Jeannie Baker learning Unit.

  • 27 May 2010 - Gilmore Primary School P21

Demolition has commenced in the Robin Klein unit, electricals have been removed and floor coverings lifted.

  • 03 Jun 2010 - Gilmore Primary School P21

Demolition is complete in the Robin Klein learning unit and construction has commenced.

  • 15 Jul 2010 - Gilmore primary School P21

The Robin Klein learning pod has been completed and handed over to the School. Demolition of the May Gibbs learning pod is nearing completion.

  • 25 Jan 2011 - Gilmore Primary School P21

The Recognition to celelbrate the completion of the Gilmore Primary School P21 BER project was held on 26 November 2010