15 Mar 2010 - Site prior to construction of Covered Outdoor Learning Area (COLA)

15 Mar 2010 - Concrete cut for COLA footings

15 Mar 2010 - COLA steel frame erected - ahead of schedule

15 Mar 2010 - First coat of paint on COLA

15 Mar 2010 - Second coat of paint nearing completion

19 Apr 2010 - COLA roof panels being installed.

23 Apr 2010 - COLA-Installation of roof panels progressing well.

03 May 2010 - COLA-Panel installation progressing well.

10 May 2010 - Installation of the ceiling panels nearing completion.

17 May 2010 - Electrical rough-ins and finishing off the end panels of the COLA.

25 May 2010 - Transparent roofing (polycarbonate sheeting)for the COLA is being installed.

03 Jun 2010 - Installation of the gutters and the transparent roofing (polycarbonate sheeting)is complete to the COLA.

15 Jun 2010 - Roofing including Polycarbonate sections complete, awaiting the louvre installation (being constructed offsite).

15 Jun 2010 - Footings for the COLA to be poured.

08 Jul 2010 - Installation of lighting is in progress for the COLA.

08 Jul 2010 - Excavation of electrical trenches have been dug ready for services.

25 Jan 2011 - Trenches completed and rainwater tanks ready for installation

25 Jan 2011 - Installation of rainwater tanks completed

25 Jan 2011 - Completed roof of COLA

25 Jan 2011 - Polycarbonate roof of COLA allows natural light to come into outdoor learning area

25 Jan 2011 - Completion of COLA

25 Jan 2011 - Completed COLA

25 Jan 2011 - Recognition Ceremony for completion of COLA

25 Jan 2011 - The Recognition Ceremony to celebrate the completion of the Gordon Primary School P21 projects was held on 24 September 2010