15 Mar 2010 - Classroom prior to refurbishment

15 Mar 2010 - Classroom stripped

15 Mar 2010 - Painting underway in POD

15 Mar 2010 - Classroom painting complete, new energy efficient lighting installed

15 Mar 2010 - POD prepared for carpet installation

15 Mar 2010 - Completed Classroom Refurbishment

15 Mar 2010 - Demolition of library verandah in progress

15 Mar 2010 - Demolition of concrete underway

15 Mar 2010 - Area cleared, ready for library extension

08 Apr 2010 - Concrete slab for Library completed.

19 Apr 2010 - Library extension slab ready for wall framing.

19 Apr 2010 - Library extension frame work nearing completion.

03 May 2010 - Library- roof framing underway.

10 May 2010 - Library-Bricks have been delivered, and roof frame under construction.

17 May 2010 - Roof trusses installed and the wall insulation is completed for the Library.

25 May 2010 - Brick work for the Library is nearing completion.

03 Jun 2010 - New extension to the Library incorporated to the existing area complete.

03 Jun 2010 - Internal wall framing in progress in the Library.

15 Jun 2010 - New extension of Library incorporated existing section.

22 Jun 2010 - Gyprock preparation and Electrical fitout in progress in the Multipurpose building.

22 Jun 2010 - Services installed for the Multipurpose building.

22 Jun 2010 - Front entrance to the library extension completed.

08 Jul 2010 - Entry of the Library extension facing the car park.

08 Jul 2010 - Preparation of Gyprock has been completed ready for painting.

08 Jul 2010 - Painting and installation of the Air Conditioning works is progressing.

08 Jul 2010 - Sports storeroom brickwork is pregressing.

08 Jul 2010 - Construction of the Green Room is nearing completion.

08 Jul 2010 - The Hall prior to partial demolition.

08 Jul 2010 - Refurbishment of the Hall has commenced.

08 Jul 2010 - Site for the new COLA to be errected.

08 Jul 2010 - Site prepared for the covered walkway.

25 Jan 2011 - Construction of COLA underway

25 Jan 2011 - Construction of COLA complete

25 Jan 2011 - Foundation work underway for covered walkway

25 Jan 2011 - Structure for covered walkway installed

25 Jan 2011 - Covered walkway near completion

25 Jan 2011 - Refurbishment of the hall progressing

25 Jan 2011 - Refurbishment of hall completed

25 Jan 2011 - Canteen refurbishment underway

25 Jan 2011 - Painting progressing and installation underway in canteen refurbishment

25 Jan 2011 - Canteen refurbishment completed

25 Jan 2011 - Painting completed and lighting installation underway in library extension

25 Jan 2011 - Computer lab 1 completed for library extension

25 Jan 2011 - Computer lab 2 finished for library extension

25 Jan 2011 - The Recognition Ceremony to celebrate the completion of the Gordon Primary School P21 projects was held on 24 September 2010