23 Feb 2010 - Site fence erected prior to bulk excavation

23 Feb 2010 - Bulk excavation commenced

23 Feb 2010 - Bulk excavation nearing completion

23 Feb 2010 - Footings poured for erection of first phase of the walkway

23 Feb 2010 - Steelwork for walkway in construction and excavation of ground to take underground rainwater tank

23 Feb 2010 - Footings being laid for main part of building

23 Feb 2010 - Block work for building commences

23 Feb 2010 - Underground rainwater tank progresses

23 Feb 2010 - Rainwater tank completed

23 Feb 2010 - Stell framework in constructed and slab laid

23 Feb 2010 - Slab work for building progresses

23 Feb 2010 - Building block work under construction

24 Mar 2010 - Block work construction well underway

06 Apr 2010 - Steel roof trusses have been fitted in some sections of the building.

16 Apr 2010 - Steel roof trusses are erected and roof purlins are being installed.

27 Apr 2010 - Roof purlins are installed.

27 Apr 2010 - Rendering to the northern section of the Multi purpose building is nearing completion.

27 Apr 2010 - structural work for stacks to support the purging of the finished building is complete.

04 May 2010 - The roof purlins have been installed.

11 May 2010 - Cement rendering of the Multipurpose building is progressing.

18 May 2010 - Greenboard has been fixed to the outside walls in preparation for cement rendering of the new Multipurpose building.

25 May 2010 - Cement rendering is nearing completion to the internal walls of the new multipurpose building.

22 Jun 2010 - Construction progressing to the Internal walls and ceiling grids of the Multipurpose building.

22 Jun 2010 - Multipurpose building internal construction progressing.

22 Jun 2010 - Multipurpose building toilet section roof being constructed.

22 Jun 2010 - All internal and external cement rendering is complete to the Multipurpose building.

25 Jun 2010 - The internal painting of the Multipurpose building has commenced.

08 Jul 2010 - Extenal painting is progressing on the Multipurpose building.

08 Jul 2010 - Internal painting of walls has commemced of the Mutipurpose building.

09 Jul 2010 - Painting is progressing and shows the air intake for the Airconditing system for Multipurpose building.

21 Jan 2011 - Painting has progressed and roof construction underway

21 Jan 2011 - Large external doors are about to be installed

21 Jan 2011 - The ceiling and heaters are being installed

21 Jan 2011 - Internal doors being fitted and gas radiant heating being installed

21 Jan 2011 - Outside final painting is about to begin

21 Jan 2011 - Walkways have been enclosed and sliding doors to the side of the building have been fitted

21 Jan 2011 - Painting in new building is progressing and all doors have been fitted

21 Jan 2011 - External building near completion as vinyl is being laid inside

21 Jan 2011 - Benches installed outside building

21 Jan 2011 - Painting completed for multipurpose building

21 Jan 2011 - Painting of the internals of the building is progressing

21 Jan 2011 - Electricians doing final fit-out in the main building

21 Jan 2011 - Ceiling near complete and installations progressing

21 Jan 2011 - Floor coverings and joinery installed in library resources room

21 Jan 2011 - Paving underway on the terrace

21 Jan 2011 - Paving of terrace complete

11 Mar 2011 - Completion of the new multipurpose building

11 Mar 2011 - Front entries to classrooms

11 Mar 2011 - The operable sliding door to devide a classroom and multipurpose hall

11 Mar 2011 - Another classroom in the multipurpose building

11 Mar 2011 - Rear view of the multipurpose building

11 Mar 2011 - Another rear view of the multipurpose building

11 Mar 2011 - The back of the multipurpose building

11 Mar 2011 - The BER Recognition Ceremony to celebrate the completion of the BER project at Monash Primary School

11 Mar 2011 - Principal Mrs Jan Walsh addressing special guests, teachers and students in the BER Recogniton Ceremony